PSC focus on NOx technical files and machinery components

International requirements on greenhouse gas (GHG) emissions are currently high in focus of Port State Control (PSC). The EIAPP certification of engines and the maintenance of records have resulted in several PSC detentions. DNV provides guidance on key PSC topics in this news.

Energy efficiency compliance after alterations or conversions

Relevant for owners and managers

GHG regulations and focus for PSC

Different PSC areas are currently scrutinizing the NOx Technical Files and the Record Book of Engine Parameters in detail to ensure the records align with the on-board installations.

During the last months, several detainable deficiencies were issued by Port State Control Officers (PSCOs) during regular PSC inspections.

PSCOs may also check available spare parts to verify if their IMO IDs match the Technical Files. Any non-compliance might trigger a more detailed PSC inspection. In case of doubt, PSCOs might also request partial disassembly of diesel generators for more thorough inspection.

Examples of common deficiencies identified during inspections include:

PSC code Defective item Additional comments by PSCOs
14601 Technical Files and, if applicable, monitoring manual NOx Technical File for main engine and generators is not available on board.
14602 Record Book of Engine Parameters Record Book of Engine Parameters properly filled in, but information related to the replacement of injection pump cylinder no. 1 as per the NOx Technical File is missing.
14606 Diesel engine air pollution control Charge air cooler of M/E is without the IMO ID number as required by the NOx Technical File.

The main grounds for past detentions were missing Technical Files or Record Books of Engine Parameters, and engine parts lacking the IMO identification number as per the Technical File on board. During follow-up on detainable deficiencies, DNV experts noted that misunderstandings and missing instructions on board were often the reasons for deficiencies, which could lead to vessel detention.

Prepare for PSC inspections

Based on the above, DNV would like to provide some guidance:

NOx Technical Files and Engine International Air Pollution Prevention (EIAPP) certificates must be available on board in their original form. Please note that for documents issued digitally, the PDF files represent the originals.

When there is a change of shipowner, care should be taken to ensure that these documents are handed over. If NOx Technical Files are missing, the owner should contact the engine manufacturer to obtain new documents. Missing certificates may be reissued by DNV.

A Record Book, or electronic Record Book, of Engine Parameters is used with the engine parameter check method to document all parameter changes, including component replacements, like-for-like replacements and engine settings, which may influence the engine’s NOx emissions. These descriptions shall be supplemented with any other applicable data used for the assessment of the engine’s NOx emissions. In principle, checking the record book is the first step for the surveyor in applying the parameter check method. This is to verify that engine parameters are within the allowable range specified in the engine’s Technical File.

The form and content of the record book is not defined. Some technical files contain templates. However, at a minimum, the date, component and old and new ID numbers should be entered, as well as changes or verifications of settings.

In case of missing or incorrect ID numbers, the shipowner should initiate corrective measures. A reasonable period should be allowed for this. In case of incorrect ID numbers, the shipowner should contact the engine manufacturer to check if approved amendments to the NOx Technical File allow the use of the components.

An inspection of the engine components and adjustable features shall be conducted as necessary. The results of this inspection, along with the documentation review, will verify that the engine’s adjustable features are within the allowable range specified in the Technical File. The surveyor may choose to check any or all of the identified components, settings or operating values.

Recommendations

DNV recommends that all customers review the items discussed in this news and to ensure updated Technical Files and Record Books are always available on board.

To be best prepared for PSC inspections, customers should also consider using DNV’s PSC Planner with its updated checklists.

References

Contact

  • For customers:
    DATE - Direct Access to Technical Experts via My Services on Veracity.
  • Otherwise:
    Use our office locator to find the nearest DNV office.